Ginzingers company extension

Ginzingers company extension

Due to an increasing lack of space, the management of Ginzinger electronic systems has decided to expand the existing company building in Weng im Innkreis in 2022 and to add a production hall. Additional space for storage and production is currently being created on around 1000 m2. The investment for the extension amounts to around six million euros.


Herbert, a new company building was actually planned. Why did things change now?

Herbert Ginzinger: Quite simply because of the current situation in the construction industry. Construction costs have increased massively. Therefore, we have deviated from our planned new building in Altheim. For the time being, we have opted for a smaller variant in order to be able to meet our production obligations. Development and customer support management will remain at the Altheim site as before. The new company building is coming, but not for several years.


Which departments are moving to the new production hall?



Herbert Ginzinger: On the approximately 1000sqm, the space on the upper floor is mainly intended for production. The additional space offers room for another SMD line, as well as for manufacturing islands for semi- and fully automated work processes, such as for THT production and the selective soldering system. We are also investing in three new storage lifts. They will then have twice the storage capacity of the previous lifts.



Storage/logistics and order picking will be expanded in the basement. Areas of the upper floor will also be used as additional storage space. Due to the construction of a truck ramp, goods receipt now takes place upstairs and there is no longer any overlapping of incoming and outgoing goods. This guarantees a better flow of materials. Furthermore, a separate storage room for hazardous materials has been planned in the basement.

 

What restrictions does the construction impose on customers?

Herbert Ginzinger: The customer will not notice anything from our conversions. The building will be completely finished, and only then will the old storage lifts be cleared out and the material stored in the new lifts. A smooth production is guaranteed. At least there will be no delivery problems due to our rebuild. ?


When will the construction work be completed?

Herbert Ginzinger: The aim is to have everything completed by July 2022.

Dear Herbert, thank you very much for the interview!

 

 